Inside ConstruckLabs / Research

A material has strength. A system needs evidence.

The research behind ConstruckSlope Plus brings soil, water, reinforcement, drainage, facing and anchorage into one investigation—so the complete assembly can be understood under field-representative conditions.

Explore the Methodology
01 / The question that shaped the programme

What happens when all the parts have to work together?

A tensile test tells us how a material responds to tension. A chamber test asks how an installed protection system behaves when the ground and water act on it.

ConstruckSlope Plus was conceived around a connected set of functions: manage water, protect the surface, mobilise reinforcement and transfer forces through designed anchors and connections. The research challenge is to examine those functions together rather than infer the behaviour of the assembly from a single material property.

The important difference is the question being tested.

Component tests remain essential. They establish properties used in selection, quality control and analysis. Full-scale chamber testing adds a different layer of evidence: the response of the actual assembly, its interfaces, its installation details and its interaction with the retained soil.

A chamber is a controlled physical test with field-representative geometry and actions. It complements field installations and monitoring; it is not an unrestricted natural mountainside or a substitute for project-specific stability assessment.

Evidence levelWhat it establishesWhy the next level matters
Material testingTensile response, stiffness, drainage capacity and other properties under defined test conditions.Individual properties do not by themselves describe the complete assembly’s response.
Connection testingBehaviour of loops, joints, attachments and anchorage details under defined actions.The ground, water and installation determine how these details are loaded in a system.
Full-scale chamberResponse of the configured soil–facing–drainage–anchor assembly under controlled water and load.Chamber boundaries, fixtures and tested conditions limit the scope of the conclusions.
Field verificationInstallation quality and behaviour in the actual ground, geometry and exposure.Completes the link from controlled research to the project’s operating conditions.
02 / Inside the chamber

Build the assembly. Introduce the challenge. Observe the response.

The latest reviewed Plus 200 method defines a severe containment investigation under sustained surcharge and a prescribed seepage programme. It is designed to observe both the facing and the load paths supporting it.

Conceptual section showing sand, facing, crest restraint, toe, water entry and separate outlets. Not to scale.Water entry through bench jointsCrest loadTEST SANDFacing + gridA / Front drainageB / Lower collectionConceptual section • not to scale • not an apparatus drawing
  • Water entry through bench joints
  • Crest load
  • Facing and grid
  • A — front drainage
  • B — lower collection
Proposed method · Rev 1 P200 · 13 Oct 2026

A defined specimen. A traceable investigation.

The reference specimen uses a 3 m retained sand height, 4 m chamber width, 6 m inward bench and a 70° face. The specified facing combines drainage, HS 200 geogrid, 3D mat and a cementitious cover, with defined crest and toe arrangements.

Two outlets separate front drainage from lower collection. Instrumentation is intended to track water movement, pressure, facing deformation, grid response, anchorage movement and toe behaviour on a common time base.

70°SPECIFIED FACE
4 × 3 mWIDTH × HEIGHT
240 hPROGRAMME WINDOW

These are method parameters, not a product rating or a reported physical pass. The reviewed method contains blank physical-result fields.

Existing product imagery / Plus 200

The components behind the chamber question.

The existing Plus 200 drainage illustration shows the product detail behind a central research question: how water travels through the facing and reaches an outlet. The chamber methodology investigates that hydraulic behaviour alongside deformation and restraint of the assembled facing.

Existing ConstruckSlope Plus 200 three-dimensional drainage detail
Plus 200 • Existing approved drainage illustration. Product visualisation, not a photograph of a physical chamber test.

Mechanical response

Face displacement, grid strain, bench settlement, loop slip and toe translation or rotation help reveal how the assembly carries load.

Hydraulic response

Measured intake, separate discharge, pressure or suction and moisture data help explain where water travels and how conditions change.

Condition evidence

Photographs, profiles, crack mapping and retained raw records connect instrument readings with the physical condition of the specimen.

03 / Why the method matters

The interfaces become visible.

The earlier CS-SPaaP 01 Rev 0 framework also addresses face rainfall and toe flooding. The specific Rev 1 P200 seepage programme does not reproduce rain impact or erosive surface flow; those claims require separate testing. The two scopes should not be combined into one claimed result.

Research paper / Calculation revision draft

Multicomponent Geo-synthetic Slope Protection and Erosion Control with Stabilizing Features

Anton Russel, Principal Author Jean-Pierre Bardet, PhD, named as Co-Author in the draft

Source manuscript dated September 2025. Calculation revision draft dated 14 October 2026.

Request the research draft

Owner-access research document. This link may require sign-in and is not a public paper download.

04 / The analytical foundation

Understand the mechanism before claiming the benefit.

The paper examines slope facing as a multicomponent problem: erosion control, water management, deformation and stabilizing features must be considered together. Its comparison investigates how changes in drainage and local water pressure can affect a facing and the adjacent soil.

The revised calculations distinguish shallow-slip equilibrium from local facing resistance and global stability. A force deficit in a soil calculation is not automatically the tensile demand on a facing; the connection to stable ground and the actual load path must be established.

The chamber provides the physical counterpart to these questions. Measured response can challenge model assumptions, identify weak interfaces and guide further design refinement. It is the link between an analytical proposition and evidence from an assembled specimen.

The draft’s worked examples are conditional calculations. They are not chamber measurements and do not establish that all shotcrete systems fail.

05 / The development journey

From a facing problem to a product-system approach.

The development story connects a practical site question with system design, analytical research and a purpose-developed test method. The chamber’s contribution is to make the next design decision evidence-led.

ConstruckSlope Plus 200

The defined chamber configuration.

View Plus 200 imagery

The reviewed Rev 1 P200 method specifies HS 200 geogrid and loop-based anchorage. It creates a defined basis for investigating this assembly’s containment, hydraulic behaviour and deformation.

  • Known component arrangement and specimen geometry.
  • Defined load and water programme.
  • Physical measurements required to assess the assumptions.
ConstruckSlope Plus 400

Shared research. Its own verification.

View Plus 400 imagery

Plus 400 belongs to the wider development programme, including different connection designs. Chamber learning can inform the engineering questions and test planning, but a Plus 200 result cannot be transferred automatically to Plus 400.

  • Document its own components and connection details.
  • Establish the applicable forces and failure mechanisms.
  • Verify the complete configuration and intended use.
Existing product imagery / Plus 400

Multiple layers. One engineered assembly.

These existing Plus 400 illustrations make the facing layers and drainage interface visible. The engineering depends on how components work together: reinforcement carries force, the facing protects the surface, and the drainage arrangement provides a route for water.

Existing ConstruckSlope Plus 400 three-dimensional facing layers
Plus 400 • Layer arrangement from the existing approved product illustration.
Existing ConstruckSlope Plus 400 drainage connection to collector pipe
Plus 400 • Drainage interface and collector detail. This image illustrates water routing; it does not depict or verify the mechanical ConstruckLock connection.

These are static illustrations from the existing product assets. They do not establish test performance or replace configuration-specific engineering drawings.

Question to component

How does water leave?

Inspect the drainage layer and its connection. Relate the visible arrangement to chamber measurements of pressure, intake and separate outlets.

Question to connection

Where does the force go?

The Plus 200 embedded rebar return and the Plus 400 mechanical details use different restraint arrangements. The connection defines the route through which reinforcement forces reach the restraint.

Question to product

How does it assemble?

Relate the component details to the complete slope design. Assembly sequence, fit, continuity and adjustment are part of the engineering—not just the appearance of the finished face.

The reviewed Plus 200 method explicitly excludes the Plus 400 C-channel or lock. Product numbers must not be read as a chamber-proven capacity or a universal slope rating.

06 / Why this matters to a project

A route to better engineering. A focus on practical delivery.

ConstruckSlope Plus is developed as an alternative approach for suitable slope-facing applications where shotcrete might otherwise be considered. The engineering objective is to combine protection, water management and a designed load path with practical installation.

Performance, speed, cost and environmental advantages depend on the specified system, access, ground, quantities and comparison basis. The reviewed chamber method does not establish universal savings, global stability or long-term service life.

07 / Reading the evidence correctly

What the chamber can tell us.

Why is this more informative than a tensile-strength figure alone?

It puts the chosen components into an assembly and observes how that assembly responds to soil, water and load. A strong geogrid cannot by itself establish drainage performance, cover retention, anchor resistance or foundation behaviour. Component testing and assembly testing answer complementary questions.

Is it a full-scale test or a field test?

It is a full-scale, controlled chamber methodology designed to reproduce selected field-relevant mechanisms. Actual installation monitoring on a natural slope adds evidence about conditions that a chamber cannot reproduce fully. Calling the chamber “field-representative” preserves that distinction.

Has this page presented a completed physical test result?

No. The reviewed 13 October 2026 method is proposed for assessment review and contains blank measurement and sign-off fields. Its retained numerical benchmarks are calculations. A completed physical result needs the specimen record, measured data, departures and signed conclusion.

Does it establish the world’s first test or the world’s only shotcrete alternative?

The records support a purpose-developed Construck method for assessing the complete SPaaP assembly. They do not independently establish worldwide priority or market exclusivity. The distinctive contribution presented here is the integrated assembly, loading, hydraulic response and reporting approach.

Can the facing replace deep stabilization measures?

Not on the basis of this chamber method. Overall slope stability must be established separately. Soil nails, anchors or other stabilization may still be required where the project analysis identifies those needs. Facing selection follows the defined engineering role.

Research record

Explore the methodology.

The primary records below distinguish the proposed physical method, the analytical draft and the public description of the research programme.